Currently In Development

Duration Compression

Defintion

Reducing the time duration of the project without reducing its scope is called Duration Compression. The two main techniques to achieve this are fast tracking (i.e. completing critical path activities concurrently), and crashing (i.e. allocating additional resources to complete an activity faster).

Comments


ATX Impact Network

About ATX Impact

We support Austin, Texas and beyond with innovative community empowerment.

Share our vision and values?

Join the ATX Impact Network

Learn More

Powered by the SUCC3SS Platform
Designed & Built by Team R3SET
© 2026 All rights reserved

Terms

Privacy